A-CDM at airports: what TOBT, TSAT and TTOT mean

Behind every on-time pushback is a timestamp system: A-CDM. We explain the acronyms from SOBT to ATOT, the 16 milestones and why a jet sometimes sits ready at the gate and waits.

Planetrack editorial teamPublished: October 15, 202615 min read

Key takeaways

  • One shared clock for everyone: A-CDM links the airport, airline, ground handler, air traffic control and the European Network Manager through shared timestamps, instead of everyone planning with their own estimates.
  • The first letter tells you how reliable the time is: S stands for scheduled, E for estimated, T for target and A for actual (measured).
  • TOBT comes from ground handling: The Target Off-Block Time is the moment when the aircraft is ready for pushback or engine start with doors closed and the jet bridge retracted.
  • TSAT comes from the system: The Target Start-up Approval Time is calculated by the departure manager from all TOBTs, runway capacity, taxi times and ATC slots – it tells the crew when to expect clearance.
  • TTOT is the forecast for liftoff: The Target Take-Off Time is, in simplified terms, TOBT or TSAT plus taxi time, and it is reported to Eurocontrol.
Contents
  1. 1.A-CDM in one sentence
  2. 2.The logic behind the acronyms
  3. 3.TOBT: the commitment from ground handling
  4. 4.TSAT: when the clearance comes
  5. 5.TTOT and CTOT: the view beyond the airport
  6. 6.The 16 milestones of a departure
  7. 7.The six building blocks of the concept
  8. 8.De-icing: when winter changes the math
  9. 9.What A-CDM means for you at the fence
  10. 10.Where A-CDM is in use
  11. 11.What to keep in mind
  12. 12.Conclusion

The Airbus has been sitting at its stand for minutes with its doors closed, the bridge is gone, the tug is attached – and nothing happens. Then, to the minute, the clearance comes and the jet pushes back. What looks like chance at the fence follows, at many large airports, a fixed schedule of acronyms: A-CDM. This guide translates TOBT, TSAT, TTOT and their relatives, shows you the 16 milestones of a departure and explains what you can read from them as a spotter.

Keep an eye on departures

Planetrack shows you weather, wind and active runways at the airport and alerts you with a sighting alert when your wish list registration is on approach. Planetrack is launching soon – join the waitlist and get early access.

Download Planetrack on the App Store Get Planetrack on Google Play

A-CDM in one sentence

Airport Collaborative Decision Making means that everyone involved in a departure works with the same times: airport operator, airline, ground handler, air traffic control and the Network Manager of Eurocontrol. In the past, every partner planned with its own assumptions – air traffic control with the flight plan, ground handling with its status at the gate, network planning with averages. A-CDM pools this information and turns it into target times that everyone aligns to.

In Europe, the concept is jointly backed by Eurocontrol, the airport association ACI Europe, the airline association IATA and the air navigation association CANSO. Eurocontrol names more efficient and robust handling on the ground as its goals, especially for turnaround and departure preparation, as well as more accurate takeoff times for planning in European airspace.

16milestones from flight plan to liftoff
35European airports with A-CDM fully implemented (according to Eurocontrol)
±15 minmaximum deviation between TOBT and EOBT before an alert is triggered

The logic behind the acronyms

Before you dive into individual timestamps, it is worth looking at how they are built. Almost all A-CDM acronyms consist of four letters, and the first one tells you how reliable the time is:

  • S – Scheduled: the planned time from the airline’s flight plan, such as the SOBT (Scheduled Off-Block Time), which belongs to the airport slot.
  • E – Estimated: an estimate that can change continuously, such as the ELDT (Estimated Landing Time) of an arriving flight.
  • T – Target: a target time that the partners agree on and align their processes to.
  • A – Actual: the time actually measured, for example the AOBT (Actual Off-Block Time) when the aircraft is really pushed back.

The rest of the acronym describes the event: OBT is off-block (leaving the parking stand), IBT in-block (arriving at the stand), LDT landing, TOT takeoff. Once you have internalized that, you can usually decode unfamiliar acronyms yourself.

Acronym Spelled out What is behind it Who provides it
SOBT Scheduled Off-Block Time planned departure time at the stand, matching the airport slot Airline / flight plan
EOBT Estimated Off-Block Time departure time according to the ATC flight plan Airline
ELDT Estimated Landing Time expected landing time of the arriving flight Network Manager, local radar data
EIBT Estimated In-Block Time expected arrival at the parking stand A-CDM system (landing plus taxi time)
TOBT Target Off-Block Time time at which the aircraft is ready for departure Airline or ground handler
TSAT Target Start-up Approval Time expected clearance for engine start / pushback Departure manager (DMAN)
TTOT Target Take-Off Time target time for takeoff A-CDM system / DMAN
CTOT Calculated Take-Off Time ATC slot when airspace is congested Network Manager
EXOT / EXIT Estimated Taxi-Out / Taxi-In Time estimated taxi time to the runway or to the stand A-CDM system
ASRT / ASAT Actual Start-up Request / Approval Time request and issue of the start-up clearance Air traffic control
AOBT / ATOT Actual Off-Block / Take-Off Time actual pushback and takeoff Air traffic control, sensors

TOBT: the commitment from ground handling

The Target Off-Block Time is the heart of A-CDM. It describes the moment when the aircraft is ready to go at its stand: all doors closed, jet bridge retracted, pushback tug ready. It is maintained by the airline or the contracted ground handler, because only they know how far catering, fueling, baggage and boarding have progressed. How many trades have to mesh here is shown in the guide to the turnaround of an aircraft.

As long as nobody has entered a TOBT manually, the A-CDM system calculates one itself: expected arrival at the stand plus minimum turnaround time (MTTT, Minimum Turn-round Time) gives an automatic TOBT. If it falls before the scheduled departure time in the flight plan, it is set to that EOBT – earlier than planned does not count as a target. As soon as the handler enters a value of their own, it overrides the automatic one.

Because the entire departure sequence hangs on the TOBT, strict rules apply at A-CDM airports. Zurich Airport describes them in its operational information, for example, like this:

  • Changes are only allowed in steps of at least five minutes.
  • The last correction must be made no later than five minutes before the current TOBT.
  • The crew must report ready to the clearance delivery position (Clearance Delivery) within five minutes before or after the TOBT.
  • Anyone who is not ready within the window is not processed further until a new TOBT has been entered.

The exact tolerances can differ from airport to airport. The principle stays the same: an overly optimistic TOBT costs not only your own flight time but also throws the sequence of all the others into disarray.

TOBT and EOBT have to match

The TOBT lives in the airport system, the EOBT in the ATC flight plan at the Network Manager. If the two are 15 minutes or more apart, the A-CDM system raises an alert to the airline or handler. Airlines can use a Eurocontrol service that automatically adjusts the EOBT to the TOBT in this case.

TSAT: when the clearance comes

The Target Start-up Approval Time is the system’s answer to all the TOBTs combined. A departure management system, DMAN (Departure Manager) for short, sorts the ready flights so that the runway is used as evenly as possible and nobody has to queue up at the holding point. According to Zurich Airport, the calculation includes the following, among other things:

  • the flight’s TOBT,
  • the available runway capacity and the assigned runway,
  • variable taxi times depending on stand and runway,
  • aircraft type, wake turbulence category and departure route,
  • any necessary de-icing,
  • ATC slots (CTOT) and special departure spacing.

According to the Eurocontrol specification, the TSAT is issued between 40 and 30 minutes before the TOBT. From then on, it is the decisive time for the crew. In Zurich, a window of plus/minus five minutes applies here too, and the tug must be coupled and ready five minutes before the TSAT so that the pushback can begin immediately after clearance.

That is exactly why you so often see aircraft at the fence that are ready and still wait: their TOBT has been reached, but their TSAT has not. Instead of standing in a queue in front of the runway with engines running, the aircraft waits at the stand. That saves fuel, noise and exhaust on the apron.

TTOT and CTOT: the view beyond the airport

The Target Take-Off Time is the time at which the aircraft is expected to lift off. The Eurocontrol specification describes it at its core as a simple addition: readiness time plus estimated taxi time, that is TOBT plus EXOT. If there is no TOBT yet, the calculation uses the expected arrival plus minimum turnaround time, and for aircraft without an inbound flight (for example from maintenance), the EOBT. If de-icing is needed, the de-icing time is added.

This TTOT is the airport’s most important gift to the European network. It is sent to the Network Manager in so-called DPI messages (Departure Planning Information):

Message Roughly when it is sent What it communicates
E-DPI from about three hours before EOBT first departure data, flight is known in the A-CDM system
T-DPI-t from two hours before EOBT and on relevant changes target takeoff time based on the TOBT
T-DPI-s after the TSAT is issued target takeoff time from the departure sequence
A-DPI at actual off-block flight is under way, takeoff time known very precisely
C-DPI on cancellation, for example a deleted TOBT previous information is invalid

The Network Manager uses this data to plan airspace. If a sector or a destination airport is overloaded, it issues a CTOT – an ATC slot, that is a narrow time window for takeoff. According to Zurich’s operational information, the standard tolerance for this is five minutes early to ten minutes late. The CTOT in turn feeds into the TSAT. What is behind airport and ATC slots is explained in the article Airport slots.

You know when it rolls – be at the right spot

On the spot map in Planetrack you find locations with directions, best light and community photos for every runway direction in use. Planetrack is launching soon – join the waitlist and get early access.

Download Planetrack on the App Store Get Planetrack on Google Play

The 16 milestones of a departure

A-CDM tracks every flight along a fixed chain of events. Each milestone triggers recalculations and can raise warnings if something does not fit together. The list goes back to Eurocontrol’s implementation manual:

1–2: Flight plan active, EOBT minus two hours

About three hours before the EOBT, the ATC flight plan is activated and the flight is created in the A-CDM system. Two hours before EOBT, the system checks whether arrival plus minimum turnaround time fits the flight plan. From here, a CTOT can be issued if there are bottlenecks.

3–6: The inbound aircraft arrives

Takeoff at the departure airport, pickup by local radar, final approach and landing: with every step the expected arrival becomes more accurate, and the automatic TOBT of the next flight moves with it.

7–8: In-block and start of ground handling

Once the aircraft is at the stand, the actual arrival plus minimum turnaround time counts. Shortly afterward, ground handling begins.

9–10: Confirm TOBT, issue TSAT

The handler confirms or corrects the TOBT. Between 40 and 30 minutes before TOBT, the departure manager calculates the TSAT.

11–12: Boarding and readiness

Boarding begins, and at the end the crew reports the aircraft ready. If no ready report arrives within five minutes after the TOBT, the responsible unit is alerted.

13–14: Start-up requested and approved

The crew requests start-up or pushback clearance (ASRT), and air traffic control grants it (ASAT). If the request does not come within five minutes after TSAT, that also triggers an alert.

15–16: Off-block and takeoff

With the pushback (AOBT), an A-DPI message goes to the Network Manager. The takeoff (ATOT) completes the chain.

Not every airport records all milestones the same way, and some – such as the moment of local radar pickup or the start of boarding – are defined locally. The order can also shift: for a long-haul inbound aircraft that took off before the two-hour mark, milestone 3 comes before milestone 2.

The six building blocks of the concept

The timestamps are only one part of A-CDM. The Eurocontrol manual divides the procedure into six elements that build on each other:

  1. Information sharing: a shared data platform for all partners.
  2. Milestone approach: the chain of events per flight described above.
  3. Variable taxi times: realistic taxi times by stand and runway instead of a flat value.
  4. Pre-departure sequencing: the departure sequence from which the TSAT arises.
  5. Adverse conditions management: procedures for snow, thunderstorms or reduced capacity.
  6. Collaborative management of flight updates: the data exchange with the Network Manager through DPI messages.

For smaller airports, there is a leaner variant called Advanced ATC Tower, which shares only part of the A-CDM data with the network.

De-icing: when winter changes the math

In winter, A-CDM becomes especially interesting. If an aircraft has to be de-iced, the system factors in additional times: when de-icing is supposed to begin, how long it takes and when it is finished. With de-icing at the parking stand, the takeoff time shifts accordingly; with de-icing on a separate pad, the system can re-sort the flights and issue new TSATs if more aircraft need de-icing than the facility can handle. Important for understanding: in Zurich, the crew must report ready within the TOBT window even if de-icing is still going on at the stand – the de-icing time is already built into the TSAT. You can read more about fluids, holdover times and procedures in the article De-icing aircraft.

What A-CDM means for you at the fence

For spotters, A-CDM is not an end in itself but a key to understanding what you see and hear.

  • Aircraft waiting at the gate: Doors closed, bridge gone, but no pushback – usually the TSAT has not been reached yet. That is not a defect but intentional.
  • Shorter queues at the holding point: Because the departure sequence is created at the gate, queues in front of the runway form less often at A-CDM airports. For you, that means taxi shots come at a more even rhythm.
  • Radio becomes easier to follow: If you listen in on the delivery or apron frequency, where that is legal, you hear ready reports and clearances in the order of the departure manager. Which frequencies exist is explained in the guide Understanding aviation radio frequencies, and the legal situation is covered under Listening to aviation radio.
  • Learning to read delays: A delayed flight at the gate can hinge on a late TOBT (ground handling not finished yet) or on a late TSAT or CTOT (runway or airspace full). The article Why flights are delayed sorts the most common causes.
  • Interpreting live data correctly: On flight tracker sites, a flight often only appears with pushback. If you know that the departure sequence is fixed half an hour earlier, you interpret the traffic picture on the map better. Background is provided by the guide Flight tracking with ADS-B for spotters.

At some airports, TOBT and TSAT are also shown on the docking system at the parking stand. In Zurich, for example, the TOBT appears there 30 minutes before the scheduled off-block time, and from five minutes before TOBT the display alternates between TOBT, TSAT and TTOT. That is intended for the crew – from the spot it is usually too far away to read along. But if you wait for the departures from Butzenbüel in Zurich, you benefit anyway: the rhythm of departures there is the result of exactly this planning.

Where A-CDM is in use

According to Eurocontrol, A-CDM is fully implemented at 35 European airports. In Germany, these include Frankfurt Airport, Munich Airport, Düsseldorf, Hamburg, Stuttgart and Berlin Brandenburg. Abroad, large hubs such as Amsterdam Schiphol, Brussels, London Heathrow, Paris Charles de Gaulle as well as Zurich and Geneva are on the list. Airports in Asia, Australia and New Zealand also work according to the concept.

Whether your home airport is on the list is not decisive for spotting itself. But it helps put the behavior on the apron in context. At the Zeppelinheim viewing platform or the Munich Airport visitors’ hill (Besucherhügel), you see the result of A-CDM every day: takeoffs in a dense, even sequence without long queues forming at the runway threshold. How many movements a runway can handle in the first place is explained in the article on airport capacity.

What to keep in mind

  • Local rules differ. Tolerance windows, display times and procedures are set per airport. The values from Zurich in this article are an example, not a Europe-wide standard.
  • TOBT is not the departure time on your ticket. The time on your boarding pass is the scheduled time. TOBT and TSAT are internal operational times.
  • TSAT is not a takeoff time. It marks the expected start-up or pushback clearance. Taxi time and, if applicable, de-icing still come before liftoff.
  • CTOT is a hard constraint. An ATC slot applies Europe-wide and cannot simply be moved by the airport. It comes from the Network Manager, not from the local air navigation service such as DFS.
  • Not every airport uses A-CDM. Smaller airfields often work without it or with the leaner Advanced Tower variant.

Do the A-CDM acronyms stick?

Check off what you could explain now – at the end you will see whether you are ready for the next round of hangar talk at the fence.

  • I know what S, E, T and A at the start of the acronyms stand for.
  • I can explain who sets the TOBT and what “ready” means here.
  • I know that the TSAT comes from the departure manager and marks the expected clearance.
  • I know the difference between TTOT and CTOT.
  • I know why a ready aircraft sometimes waits at the gate.
  • I can roughly explain how de-icing shifts takeoff times.

Log every departure

Post your sightings with photo, aircraft type, registration, airline and spot, collect them in your hangar and swap notes with the community. Planetrack is launching soon – join the waitlist and get early access.

Download Planetrack on the App Store Get Planetrack on Google Play

Conclusion

A-CDM turns many individual estimates into a shared timeline. With the TOBT, ground handling says when the aircraft is ready, the departure manager answers with the TSAT when it may go, and the TTOT tells the European network when the aircraft will be airborne. Sixteen milestones hold this chain together, from the activated flight plan to liftoff. Anyone who knows the acronyms sees more at the fence than just waiting and taxiing aircraft – they recognize the planning behind it.

Quick verdict

TOBT means “we are ready”, TSAT means “now you may go”, TTOT means “that is roughly when it lifts off”. Everything else is a variation of these three times, recognizable by the first letter: S scheduled, E estimated, T target, A actual.

Summary

  • A-CDM is a procedure backed by ACI Europe, Eurocontrol, IATA and CANSO that links ground handling and departure planning through shared data.
  • The sequence of every flight is divided into 16 milestones – from the activation of the flight plan to liftoff.
  • TOBT, taxi time, runway capacity and any ATC slots produce the departure sequence on the apron, which is reflected in each flight’s TSAT.
  • For spotters, A-CDM explains why aircraft wait at the gate with their doors closed, why there are shorter queues at the holding point and why pushback times at large airports are surprisingly predictable.

Frequently asked questions

What does A-CDM mean?

A-CDM stands for Airport Collaborative Decision Making. It is a procedure in which airport operators, airlines, ground handlers, air traffic control and the European Network Manager share their data on every departure in real time. The goal is better use of runways, stands and staff, as well as more reliable takeoff times for the European network.

What is the TOBT?

The Target Off-Block Time is the time at which an aircraft is, according to the airline or handler, ready for pushback or engine start: all doors closed, jet bridge retracted, tug ready. The TOBT is maintained by the airline or its handling agent and is the basis for all further calculations.

What is the TSAT?

The Target Start-up Approval Time is the time at which a crew can expect engine start or pushback clearance. It is calculated from the TOBT by the departure management system (DMAN) and takes into account runway capacity, taxi times, wake turbulence separation, de-icing and ATC slots, among other things. According to the Eurocontrol specification, it is issued between 40 and 30 minutes before the TOBT.

What is the difference between EOBT and TOBT?

The EOBT (Estimated Off-Block Time) is in the ATC flight plan and is filed by the airline. The TOBT is the continuously updated readiness time from ground handling. The two are supposed to match: if they differ by 15 minutes or more, the A-CDM system raises an alert so that one of the two times is adjusted.

How are TTOT and CTOT related?

The TTOT is the target takeoff time calculated by the airport, in simplified terms TOBT or TSAT plus estimated taxi time. The CTOT (Calculated Take-Off Time) is an ATC slot that the Network Manager issues when airspace is congested. The TTOT feeds into the CTOT calculation, and an existing CTOT is in turn taken into account when calculating the TSAT.

Which airports use A-CDM?

According to Eurocontrol, A-CDM is fully implemented at 35 European airports. In Germany these include Frankfurt, Munich, Düsseldorf, Hamburg, Stuttgart and Berlin Brandenburg, and in Switzerland Zurich and Geneva. There are also A-CDM airports outside Europe, for example in Asia and Australia.

Can I see TOBT and TSAT as a spotter?

The times are mainly displayed in the systems of the operational partners. At some airports, such as Zurich, TOBT and TSAT also appear on the docking system at the parking stand – intended for the crew, not for spectators. What you can hear publicly are the effects on the radio: clearances for engine start and pushback come in the order set by the departure manager.

PT

Planetrack editorial team

We build the Planetrack app and go spotting ourselves – on observation decks, under approach paths and at the fence. Every guide is based on our own experience and is updated regularly.

More articles in Airport operations →

Read more in Airport operations

Related airports & manufacturers

Airports, manufacturers, airline groups and alliances – who is behind them and what you should know as a spotter.

All airports & manufacturers →

Related spotting locations

Specific vantage points with the runway configuration, light times, coordinates and an honest take on whether the trip is worth it.

All spotting locations at a glance →